Beaumeade Data Center

Beaumeade Data Center
Montgomery Village, MD

 

Project type: New Construction

Services Completed: Concrete, Stone Installation and paving

Size: 6000+ tons of stone, 4000 tons of asphalt, 1300cu of concrete.

 

The Problem:
Data centers have an aggressive schedule that allowed us only 5 working months from pre-construction to final completion. We also were faced with other contractors working in the same area which required the job to be done in phases.

 

The Solution:
We installed 6” of stone and 5” of asphalt. Concrete work included new sidewalks, curb and gutter with thicknesses between 4-8”.